Radiant Floor Heat in a Concrete Slab

In-floor heat turns a slab into a big, even radiator. It also means the pour has to protect hundreds of feet of tubing you can never get back to. Here's how the pieces fit together.

  • Updated October 2026
  • By Nate Bennett's crew
  • Central New York
Free estimates

Get a Free Estimate

Only your name and phone are needed. We'll call you back.

By Bennett's Concrete and Excavation, Norwich, NY. Updated October 2026.

How it works

Warm water from a boiler or heat pump circulates through PEX tubing embedded in the slab. The concrete soaks up that heat and gives it back slowly and evenly across the whole floor. It's popular in shops, garages, barns and barndominiums because the heat is where your feet are, and the floor stays warm even when overhead doors open.

The Radiant Professionals Alliance (RPA) guidelines limit fluid temperature to 140°F in concrete thermal mass unless the tubing maker approves otherwise. Your heating designer sets the temperatures, tube spacing and loop layout.

The layers, from the ground up

  1. Compacted crushed stone base.
  2. Vapor retarder.
  3. Rigid foam insulation board.
  4. Reinforcement, if the slab design calls for it.
  5. PEX tubing, tied or clipped in loops to the layout.
  6. Concrete, placed and finished around and over the tubing.

On the barndo floor we poured in Holland Patent, about 60 yards of concrete, the radiant tubing was laid on insulation board before the pour.

Insulation under the slab

Without insulation, much of the heat goes down into the ground instead of up into the room. RPA's slab-on-grade guidelines list several approaches, including R-5 under the entire slab and slab edge, or R-5 extending 4 feet horizontally or vertically at the perimeter. The energy code has its own requirements for heated slabs, so your designer and code officer should confirm what applies to your building.

Pressure test before and during the pour

Once concrete covers a leak, fixing it means breaking out the slab. RPA's guidelines call for pressure testing the tubing at 100 psi for at least 30 minutes, then reducing to 30 psi before the concrete is poured, so the system stays under pressure while the concrete goes in. A drop on the gauge during the pour points to damage that can be found and fixed right away.

RPA also says there should be no tubing joints in the slab, and any repair during the pour must use a factory-approved fitting.

Depth, joints and saw cuts

RPA calls for tubing in a structural slab to sit at least 2 inches below the surface. Where tubing crosses an expansion joint, it should be sleeved at least 4 inches on each side of the joint.

Control joints need planning too. NRMCA says saw cut joints should be at least one-quarter of the slab thickness deep. That cut must stay above the tubing, so the tubing layout, the joint layout and the slab thickness all have to agree before the pour. A marked-up plan showing loop routes and joint lines prevents a very expensive mistake.

Decisions to make before the tubing goes down

  • Zones: a living area, a shop bay and a garage bay may each want their own loop and thermostat.
  • Manifold location: usually on an interior wall where it can be reached and won't be blocked later.
  • No-tubing areas: places where you'll drill into the floor, like lift anchors, racking, equipment bolts or interior wall plates, should stay clear of tubing.
  • Drains and plumbing: floor drains and plumbing stubs are set first so tubing can route around them.
  • Door openings: where tubing runs near overhead doors, and how the slab edge there is insulated.
  • Sensors: many systems use a floor sensor that has to be placed before the pour.

Write these on the plan, take photos of the tubing before the concrete goes in, and keep them. Years later, those photos tell you where it's safe to drill.

Pour day

  • The heating contractor confirms the tubing is under pressure and the manifold locations are protected.
  • The crew walks carefully and keeps wheelbarrows, hoses and tools off the tubing where possible.
  • A pump truck often places the concrete on big floors, which keeps trucks and chutes off the layout.
  • The slab is screeded, floated and power troweled like any interior floor.
  • Joints are cut to the planned layout and depth.

Heating it up and next steps

Ask your heating contractor when the system can be started and how fast to bring it up to temperature; the tubing maker's instructions govern. Bennett's pours pole barn and barndo floors and slabs over radiant tubing laid out by your heating contractor. See also the pole barn floor guide and vapor barriers under slabs.

Questions

Straight answers.

Don't see yours? Call (607) 244-5118. You'll talk to the people doing the work.

Can radiant heat be added to an existing concrete slab?

Not inside it. Tubing goes in before the pour. Existing floors need a new slab or an overlay system over the old one.

Do I need insulation under a radiant slab?

Yes. RPA's guidelines include R-5 under the entire slab and edge as one option, and the energy code sets requirements for heated slabs.

How deep should radiant tubing be in a slab?

RPA calls for at least 2 inches below the surface in a structural slab, and it must stay below the depth of saw cut control joints.

Who lays out the radiant tubing?

The heating contractor designs and installs the tubing and manifold. The concrete crew protects it during the pour.

Free estimates

Have a project in mind?

(607) 244-5118

Call or text, or send the form. Tell us what you're thinking and where the job is, and we'll get back to you.

Based in
Norwich, NY
Free estimates

Tell us about the job

Only your name and phone are needed. We'll call you back.

Call NowFree Estimate